Stieger Lake Ln Street & Parking Improvements
Project Description
The proposed Stieger Lake Lane Street and Parking Improvement project, is a full street reconstruction project that will be broken into two phases. The first phase (Stage 2) is proposed for construction in 2018 from approximately City Hall to Enki Brewery and would include reconstruction of the street and storm sewer system, improvements to the sanitary sewer and watermain systems, construction of sidewalk and streetscape amenities along the south side of the roadway, and 25 new on-street parking stalls along the south side of the roadway.

Sign up to receive email or text updates.

Project Meetings
February 7, 2018:  Property Owner Meeting
March 8, 2018: Property Owner Open House (individual mailings)

City Council Items
May 22, 2017: Authorize Preliminary Design
November 27, 2017: Authorize Final Design
March 12, 2018: Receive and Accept Feasibility Report and Call for Public Improvement Hearing; Authorize burying of Overhead Lines
April 9, 2018: Hold Public Improvement Hearing and Order the Improvements; Approve Plans and Specifications; Call for Final Assessment Hearing (Final Assessment Notice)
May 29, 2018: Accept Bids and Award Contract; Hold Final Assessment Hearing, Authorize Geotechnical Testing Services

Project Updates
July 17, 2018: Project Update